Construction dynamics of Family Plaza: February – April 2023
We are actively building for your happy and carefree life in the brand new apartments of the Family Plaza residential complex. The complex continues to grow dynamically from month to month. The first sections are being prepared for commissioning, and new sections are constantly growing. See for yourself.
In February-April of this year, it was completed:
Section 1
Finishing of the hall is completed.
Handed over to the management company.
Section 2
Finishing of the entrance and hall is completed.
Handed over to the management company.
Section 3
Finishing of the entrance is in progress.
Section 4
Finishing of the entrance is in progress.
Section 5
Plastering of apartments is completed.
Facade finishing is in progress.
Works on internal house networks (electricity supply) are in progress.
Plastering of the staircase and garages has begun.
Works on finishing the entrance have begun.
Section 6
Completed works on internal house networks (water supply and sewerage).
Glazing has been completed.
Plastering of apartments is completed.
Facade finishing is in progress.
Section 7
The 9th and 10th floors have been erected.
Exterior walls of the 6th and 7th floors have been erected.
The internal walls of the 6th floor have been laid and the laying of the internal walls of the 7th floor is in progress.
Glazing of the floors has begun and is in progress.
Section 8
The 2nd-4th floors have been erected.
Exterior walls of the 1st and 2nd floors have been erected.
The internal walls of the 1st floor have been laid and the laying of the internal walls of the 2nd floor is underway.
Sections 9-10
The development of the pit is completed.
Reinforcement of the foundation slab has been completed.
Concreting of the vertical elements of the basement is 90% complete.
Section 12
Work is underway on the in-house networks (electricity).
Commercial glazing has been completed.