Construction dynamics of RC A5: January – March 2023

Construction dynamics of RC A5: January – March 2023
We report on the growth of the modern business-class residential complex in the heart of Ivano-Frankivsk, the A5 residential complex. Our team builds so quickly that the dynamics are noticeable in just a few months. Compare for yourself. As of January this year, we have completed the project: The 7th and 8th floors were built. Concreting of the vertical elements of the 9th floor has been completed. Reinforcement of the floor slab on the 9th floor is in progress. The outer walls of the 3-5th floors have been constructed. Laying of the outer walls of the 6th floor has begun. The internal walls of the 3-5th floors are being constructed. The laying of the internal walls of the 6th floor continues. We continue to create an innovative space for comfortable living in the city.