Construction dynamics of the A5 residential complex: April – August 2023
Take a look at how sections 1 and 2 of the A5 business class residential complex have grown. In 7 months of non-stop work, we managed to complete the construction of all floors and start construction of the next section - the third one. Amazing pace and great results!
Check out the progress since February 2023:
Sections 1-2
The 8th to 11th floors have been erected.
Exterior walls of the 4th-11th floors have been erected.
The internal walls of the 4th-7th floors have been built.
The internal walls of the 8th and 9th floors are 40% complete.
Works on the facade are in progress.
Glazing of the 3rd-9th floors has been completed.
Glazing of the 10th floor is in progress.
Plastering of apartments has begun and is in progress.
Works on the commercial roof are in progress.
Facade construction has begun and is in progress.
Section 3
Construction of the section has begun and is actively underway.
The basement, 1st and 2nd floors have been completed.
The construction of the 3rd floor is in progress.