Construction dynamics of the residential complex “A5”: April 2022 – February 2023

Construction dynamics of the residential complex “A5”: April 2022 – February 2023
No matter what happens, the blago team continues to work and change the city. The construction of the A5 business class residential complex continues at a steady pace and consistency.   Since April last year, the following stages have been completed: 7 floors have been built and work is underway on the 8th floor. The outer walls of the 2nd-4th floors have been built. The exterior walls of the 5th floor are 60% complete. The internal walls of the 2nd and 3rd floors have been laid. The laying of the internal walls of the 4th floor is in progress.   We focus on the result. We focus on creating a modern urban space for comfortable living in the city center.