Construction dynamics of the U ONE residential complex: March – June 2023
To build a residential complex and see the result is our goal.
Buying an apartment and seeing its rapid construction is your reality.
That is why we have prepared two angles with the dynamics at the construction site of the U ONE residential complex.
Section 3
Installation of vertical elements of the 11th floor continues.
Installation of vertical elements of the 7th, 8th, 9th, 10th floors is completed.
Installation of the floor slab of the 7th and 8th floors is completed.
Completion of the internal walls of the 2nd, 3rd, 4th floors.
Completion of the exterior walls of the 3rd, 4th, 5th floors.
Completed glazing of the 2nd, 3rd, 4th floors.
Laying of the outer walls of the 6th and 7th floors has begun.
Section 4
Installation of vertical elements of the 2nd, 3rd, 4th, 5th, 6th floors is completed.
Installation of the floor slabs of the 3rd, 4th, 5th, 6th, 7th floors is completed.
Laying of the exterior walls of the 2nd floor has been completed.
Laying of the internal walls of the 2nd floor is in progress.
Section 2
Installation of monolithic grillage of the 1st floor is completed.
The installation of vertical elements of the 1st floor has been completed.
Installation of formwork for the floor slab of the 2nd floor is completed.
Installation of the floor slab of the 3rd floor is in progress.
Installation of monolithic grillage is in progress.
Section 1
Works on pressing reinforced concrete piles have been completed.
Installation of monolithic grillage is in progress.