Construction dynamics of the U ONE residential complex: February – April 2023
Despite the cold and snowy spring, it is hot at the U ONE construction site. The equipment is working at full capacity, and the highly skilled builders are tirelessly implementing the planned projects. High-quality, fast and with strict adherence to the project.
Since February this year, it has been completed:
Section 3
The 2nd-6th floors have been completed.
The construction of the 7th floor is underway.
The outer walls of the 2nd and 3rd floors have been built.
Laying of the outer walls of the 4th floor has begun.
The internal walls of the 2nd floor have been laid.
Laying of the internal walls of the 3rd floor has begun.
Section 4
Completed work on pressing reinforced concrete piles.
Completed work on the installation of monolithic grillage.
The 1st-3rd floors have been erected.
Installation of vertical elements of the 4th floor has begun.
Section 2
Reinforced concrete piles have been pressed in.
The installation of monolithic grillage of the 1st floor has been completed.
Installation of vertical elements of the 1st floor is 80% complete.
Section 1
Construction of the section has begun.
Works on pressing reinforced concrete piles have been completed by 80%.
We continue to change the city and create technological real estate for your quality of life.