Construction dynamics of the U ONE residential complex: March – July 2023
It is better to see once than to hear four times. These photos show the progress in the construction of the U ONE residential complex over four months.
What was accomplished during this period?
Section 3
The installation of vertical elements from the 8th to the 10th floor has been completed.
Installation of the floor slab from the 7th to the 13th floor is completed.
Laying of external walls from the 4th to the 10th floor is completed.
Completed laying of the internal walls of the 3rd, 4th, 5th floors.
Laying of external walls from the 6th to the 9th floor has begun.
Glazing from the 2nd to the 6th floor has been completed.
Glazing of the 7th floor is in progress.
Section 4
Installation of vertical elements from the 4th to the 10th floor is completed.
Laying of external walls from the 2nd to the 4th floor is completed.
Installation of the floor slab from the 7th to the 9th floor is completed.
Completed laying of the internal walls of the 2nd floor.
Glazing of the 2nd floor is completed.
Installation of vertical elements of the 10th floor is in progress.
Section 2
Installation of monolithic grillage of the 1st floor is completed.
Installation of vertical elements of the 1st floor is completed.
Installation of formwork for the floor slabs of the 1st and 2nd floors is completed.
Installation of floor slabs from the 3rd to the 5th floor is completed.
Installation of vertical elements of the 6th floor is in progress.
Section 1
Reinforced concrete piles have been pressed into place.
Installation of monolithic grillage is in progress.
Installation of monolithic grillage is 90% complete.
Installation of vertical elements of the 1st floor is 60% complete.