Construction state of the Chocolate residential complex as of 11.06.2021
Sections 1,2
Bricklaying of the outwall and internal walls is complete.
Installation of windows is in progress.
Roofing has begun.
Finishing of the façade has begun.
Sections 3,4
Concrete casting of the floor slab panel of the 6th floor is in progress.
Bricklaying of the outwall and internal walls of the 3rd floor is in progress.
Section 5
Concrete casting of the vertical members of the basement level is complete.
Backfilling is in progress.