Construction state of the Comfort Park residential area as of 21.032023
Section 13
Installation of stair railings has been completed.
Reinforcement of the gas pipe along the facade is underway.
Section 14
Tile installation on the balconies is nearing completion.
Section 16
Tiles on the balconies are 60% complete.
Installation of stair railings is completed.
Section 17
Plastering of walls in the apartments is 60% complete.
Section 18
Finishing of the facade is completed.
Gas communications have been installed by 70%.
Plastering of walls in the apartments is completed.
Section 19
Installation of windows on the 2nd and 3rd floors is completed.
Installation of windows on the 4th floor is 50% complete.
Installation of formwork, reinforcing mesh and floor slabs of the 7th, 8th and 9th floors is completed.
Installation of formwork, reinforcing mesh and floor slab on the 10th floor is 50% complete
The masonry of the outer walls of the 4th and 5th floors has been completed.
Laying of the outer walls of the 6th floor is 50% complete
Masonry of the storerooms in the basement is 100% complete.
The masonry of the interior and inter-apartment walls of the 2nd floor is 100% complete.
Section 20
The installation of formwork, knitting of reinforcing mesh and floor slabs on the 4th and 5th floors is 100% complete.
Installation of formwork, reinforcing mesh and floor slab of the 6th floor is 50% complete.
Laying of the outer walls of the 1st and 2nd floors is nearing completion.
Laying of the outer walls of the 3rd floor is 50% complete.