CONSTRUCTION STATE OF THE COMFORT PARK RESIDENTIAL COMPLEX AS OF 17.06.2021
Sections 10-12
Finishing of the façade is in progress.
Apartment plastering is complete.
Renovation of the stairwell is in progress. Installation of garage doors is almost complete.
Section 13
Concrete casting of the vertical members of the 11th floor is almost complete.
Bricklaying of the outwall of the 7th-8th floor is complete.
Bricklaying of the internal walls of the 7th floor has begun.
Section 15
Concrete casting of the vertical members of the 4th floor is in progress.
Section 16
Concrete casting of the 9th floor slab panel is in progress.
Bricklaying of the outwall of the 4th floor is in progress.
Section 17
Preparation to the concrete casting of the vertical members of the ground floor is in progress.
Section 18
Concrete casting of the vertical members of the ground floor is complete.