Construction state of the Family Plaza residential complex as of 16.05.2023
01 /01
Section 1
Transferred to the management company.
Section 2
Transferred to the management company.
Section 3
Finishing of the entrance is completed. Finishing of the hall has begun.
Section 4
Finishing of the entrance is 95% complete. Finishing of the hall has begun.
Section 5
The facade is 95% finished.
Works on in-house networks (electricity supply) have been completed by 80%. Plastering of the staircase and garages is completed.
The entrance has been finished by 30%.
Section 6
Facade finishing is 90% complete.
Plastering of the staircase and garages is completed.
Work has begun on the in-house networks (electricity).
Section 7
The masonry of the external walls of the 10th floor has been completed. Laying of the internal walls of the 8th and 10th floors is in progress. Glazing of the 7th floor is 40% complete.
Section 8
Concreting of vertical elements of the 6th floor is completed. Concreting of the floor slab of the 6th floor is in progress. Completed laying of the internal walls of the 2nd floor.
Sections 9-10
Concreting of vertical elements of the 1st residential floor is 90% complete. Installation of formwork for the floor slab of the 1st residential floor is underway.
Section 12
Work is underway on the in-house networks (electricity supply).