Construction state of the Family Plaza residential complex as of 19.04.2023
Section 1
Transferred to the management company.
Section 2
Transferred to the management company.
Section 3
The entrance is 85% finished.
Section 4
Finishing of the entrance is 85% complete.
Section 5
The facade is 95% finished.
Works on in-house networks (electricity supply) have been completed by 60%.
Plastering of the staircase and garages has begun.
Works on finishing the entrance have begun.
Section 6
Plastering of apartments has been completed.
The facade is 80% finished.
Works on in-house water and sewerage networks have been completed.
Section 7
Concreting of the floor slab of the 10th floor is completed.
Laying of the external walls of the 7th floor is completed.
Laying of the internal walls of the 7th floor is in progress.
Glazing of the 5th floor is completed.
Section 8
Concreting of vertical elements of the 5th floor is completed.
Completion of the exterior walls of the 2nd floor.
Laying of the internal walls of the 2nd floor is in progress.
Sections 9-10
Concreting of the vertical elements of the basement is 90% complete.
Section 12
Work is underway on the in-house networks (electricity).
Commercial glazing is completed.
Finishing of the entrance is 30% complete.
Find out first about the company's news