Construction state of the Family Plaza residential complex as of 20.03.2023
Section 1
Transferred to the management company.
Section 2
Finishing of the hall is completed.
Section 3
Finishing of the entrance is 70% complete.
Section 4
Finishing of the entrance is 70% complete.
Section 5
The facade is 80% complete.
Works on in-house networks (electricity supply) have been completed by 40%.
Plastering of apartments is completed.
Section 6
Glazing is completed.
Works on plastering of apartments have begun.
Facade finishing is 60% complete.
Section 7
Concreting of vertical elements of the 9th floor is underway.
Completion of the exterior walls of the 6th floor.
Completed laying of the internal walls of the 6th floor.
Glazing of the 2nd floor has begun.
Section 8
Concreting of the floor slab of the 3rd floor is underway.
Laying of the exterior walls of the 1st floor is completed.
Completed laying of the internal walls of the 1st floor.
Sections 9-10
The development of the pit is completed.
Reinforcement of the foundation slab is underway.
Section 12
Work is underway on the in-house networks (electricity).
Commercial glazing is 90% complete.
Parking lot
Concreting of the parking lot floor slab is completed.