Construction state of the Family Plaza residential complex as of February 20, 2023
Section 1
Transferred to the management company.
Section 2
Finishing of the entrance is completed.
Finishing of the hall is completed.
Section 3
Finishing of the entrance is 60% complete.
Section 4
Finishing of the entrance is 60% complete.
Section 5
The facade is 70% complete.
Works on in-house networks (electricity supply) have been completed by 30%.
Plastering of apartments is 70% complete.
Section 6
Glazing is 70% complete.
Works on internal house networks (water supply and sewerage) are completed.
The facade is 30% complete.
Section 7
Completion of the exterior walls of the 6th floor.
Laying of the internal walls of the 6th floor has begun.
Section 8
Concreting of vertical elements of the 2nd floor is completed.
Completed laying of the exterior walls of the 1st floor.
Laying of the internal walls of the 1st floor is 70% complete.
Sections 9-10
The development of the pit is 80% complete.
Preparatory work is underway.
Section 12
Work is underway on the internal house networks (electricity supply).
Commercial glazing has begun.
Parking lot
Concreting of the floor slab of the parking lot of the second bay is completed.