Construction state of the IQ House residential complex as of 24.10.2023
Section 1
Reinforcement of the floor slab on the 8th floor has been completed.
Waterproofing of the foundation is 70% complete.
Installation of formwork for the floor slab of the 10th floor has begun.
Concreting of the walls and columns of the 10th floor has been completed.
Concreting of the staircases of the 9th floor has been completed.
Plastering of the electrical and water metering units has been completed.
Section 2
Installation of windows on the 9th floor has been completed.
Completed laying of interior and inter-apartment walls on the 8th floor.
Laying of the interior and inter-apartment walls of the 8th floor has begun.
Facade works have been completed by 25%.
The waterproofing of the foundation is 50% complete.
Plastering of electrical and water metering units has been completed.
Section 3
Plastering of the 1st floor is completed.
Plastering of the 2nd and 3rd floors is in progress.
The laying of the parapet has been completed.
Waterproofing of the foundation is 70% complete.
Laying of interior and inter-apartment walls of the 7th floor is completed.
Laying of ventilation chimneys has begun.
Plastering of electrical and water metering units has been completed.