0
We will call you back in 25 seconds
Order a call

Construction state of the IQ House residential complex as of 26.04.2023

Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023
Construction state of the IQ House residential complex as of 26.04.2023

01 /01

Section 1 The construction of vertical elements of the 3rd floor is completed. Concreting of the floor slab of the 3rd floor has been completed. Section 2 Concreting of the floor slab of the 7th floor is completed. Laying of external walls of the 4th floor is completed. Laying of the internal walls of the 3rd floor is in progress. Installation of windows on the 2nd and 3rd floors is completed. Section 3 Completed laying of the external and internal walls of the 2nd floor. The construction of the floor slab of the 6th floor continues. Laying of the external walls of the 3rd floor has begun.
envelope

Find out first about the company's news