Construction state of the IQ House residential complex as of 28.06.2023
Section 1
Completed laying of the outer walls of the 2nd floor.
Installation of the floor slab of the 4th floor is completed.
Installation of windows on the 1st floor is completed.
Section 2
Laying of the internal walls of the 6th floor is 80% complete.
Installation of vertical elements of the 8th floor has begun.
Installation of the floor slab of the 7th floor is completed.
Section 3
Laying of the external walls of the 5th floor continues.
Installation of windows on the 4th floor is completed.
Installation of the floor slab of the 6th floor is completed.
Installation of vertical elements of the 7th floor has begun.