Construction state of the Main House residential complex as of 06.07.2021
Sections 3,4
Finishing of the façade is complete.
Renovation of the stairwells and installation of lifts are in progress.
Plastering of garages and garage doors is almost complete.
Installation of garage doors is almost complete.
Section 1
Concrete casting of the vertical members of the 7th floor is complete.
Installation of the vertical members of the 8th floor is in progress.
Bricklaying of the outwall and inner walls of the 2nd, 3rd and 4th floors is in progress.
Concreting of stairways of the 6th floor is complete.
Section 2
Concrete casting of the vertical members of the 7th floor is complete.
Concreting of stairways of the 6th floor is complete.