Construction state of the Main House residential complex as of 15.06.2021

Construction state of the Main House residential complex as of 15.06.2021
Construction state of the Main House residential complex as of 15.06.2021
Construction state of the Main House residential complex as of 15.06.2021
Construction state of the Main House residential complex as of 15.06.2021

01 /01

Sections 3,4 Finishing of the façade is almost complete. Renovation of the stairwells is in progress. Plastering of garages is almost complete. Installation of garage doors is almost complete. Section 1 Concrete casting of the floor slab panel of the 6th floor is complete. Concrete casting of the vertical members of the 7th floor is in progress. Bricklaying of the outwall and inner walls of the 3rd floor is in progress. Section 2 Concrete casting of the vertical members of the 6th floor is in progress.