Construction state of the Manhattan UP residential area as of 10.04.2023
Section A1
Glazing of the 9th and 10th floors has begun.
Facade works are underway.
Plastering of apartments with gypsum plaster continues.
Plastering of corridors of staircases and storerooms has begun.
Section A2
Concreting of vertical elements of the 12th residential floor continues.
The masonry of the 8th residential floor is completed.
Laying of the outer walls of the 9th residential floor has begun.
Section A3
Installation of vertical elements of the 7th floor is completed.
Reinforcement of the floor slab of the 7th floor is in progress.
Laying of the internal walls of the 3rd floor is completed.
Laying of the outer walls of the 4-5 residential floors is in progress.
Section A4
Installation of vertical elements of the commercial floor is completed.
Reinforcement of the floor slab of the 0th commercial floor is in progress.
Parking lot
Concrete work on the parking lot has been completed.