Construction state of the modern district Manhattan as of 17.06.2021
Building 3
Finishing of the façade is almost complete.
Installation of drop aprons is in progress.
Renovation of lobbies and stairwells is in progress.
Bricklaying of the pantries on the ground floor is in progress.
Building 4
Bricklaying of the internal walls of the 8th floor is complete.
Bricklaying of the outwall of the 13th floor is in progress.
Carcassing is complete.
Building 5
Bricklaying of the internal walls of the 9th floor is in progress.
Bricklaying of the outwall of the 12th floor is complete.
Bricklaying of the roof parapet is complete.
Building 6
Concrete casting of the floor slab panel of the ground floor is in progress.
Building L1
Carcassing of all floors is complete.
Roofing is in progress.
Installation of windows is in progress.
Bricklaying of the outwall of the 14th-15th floors has begun.
Bricklaying of the internal walls of the 14th floor has begun.
Building L2
Concrete casting of the 7th floor vertical members is almost complete.
Bricklaying of the outwall of the 3rd floor is complete.
Bricklaying of the internal walls of the 3rd floor is in progress.
Building L3
Excavation of the pit is complete.