Construction state of the Parkova Alley residential complex as of 24.05.2023
Section 3
Facade works are 60% complete.
Interior finishing works are in progress.
Section 3a
The facade is 70% complete.
Works on the installation of internal electrical networks have been completed.
Works on the installation of internal water supply and sewage networks have been completed.
Section 3b
Installation of vertical elements of the 5th floor continues.
Installation of the floor slab of the 4th floor is completed.
Laying of external and internal walls of the 2nd floor has begun.
Section 3c
Installation of the floor slab of the 5th floor is completed.
Installation of vertical elements of the 4th floor is completed.
Section 3d
Installation of the foundation slab is completed.
Section 4
Handed over to the management company.
Section 5
Transferred to the management company.
Landscaping
Landscaping of the territory has been completed.