Construction state of the Parkova Alley residential complex as of 25.04.2023
Section 3
The plastering of the 6th floor apartments has been completed.
Works on the installation of internal electrical networks have been completed.
Works on the installation of internal water supply and sewage networks have been completed.
Facade works have been completed by 30%.
Installation of industrial floor is completed.
Section 3a
Roof installation is completed.
Glazing of the 6th floor is completed.
The facade is 40% complete.
Works on the installation of internal electrical networks are in progress.
Works on the installation of internal water supply and sewerage networks are in progress.
Section 3b
Installation of vertical elements of the 4th floor continues.
Installation of the floor slab of the 3rd floor is completed.
Section 3c
Installation of the floor slab of the 3rd floor is completed.
Installation of vertical elements of the 3rd floor is completed.
Section 4
Transferred to the management company.
Section 5
Handed over to the management company.
Landscaping
The paving of sections 4, 5, 6, 7 has been completed.