Construction state of the Parkova Alley residential complex as of 26.06.2023
Section 3
Facade works have been completed by 80%.
The interior decoration is 60% complete.
Section 3a
The facade is 90% complete.
Work on interior decoration has begun.
Section 3b
Installation of vertical elements of the 5th floor is completed.
Installation of the floor slab of the 6th floor is in progress.
Laying of external and internal walls of the 2nd floor is in progress.
Section 3c
Installation of the floor slab of the 7th floor is completed.
Laying of the internal walls of the 2nd floor is in progress.
Section 3d
Installation of the foundation slab is completed.
Section 3e
The excavation of the pit is completed.