Construction state of the Parkova Alley residential complex as of 27.03.2023
Section 3
The masonry of the exterior and interior walls of the 11th floor has been completed.
Plastering of apartments on the 6th floor is in progress.
The glazing of the 10th floor has been completed.
Work has begun on the installation of internal electrical networks.
Work has begun on the installation of internal water supply and sewage networks.
Facade works are in progress.
The roof has been completed.
Section 3A
Roof installation is in progress.
Glazing of the 6th floor is in progress.
Facade works are in progress.
Completed laying of internal and external walls of the 11th floor.
Section 3B
Installation of vertical elements of the 3rd floor continues.
Installation of the floor slab of the 2nd floor is completed.
Section 3C
Installation of the floor slab of the 2nd floor is in progress.
Installation of vertical elements of the 2nd floor is completed.
Section 4
The interior decoration of the entrances is completed.
Section 5
Interior decoration of the entrances is completed.
Landscaping
Paving of pavement near sections 4, 5, 6, 7 is in progress.