Construction state of the Parkova Alley residential complex as of 28.09.2023
Section 3
Interior finishing works are 90% complete.
Installation of doors has begun.
Gas supply to the apartments has begun.
Concreting of the concrete screed of the basement storerooms has begun.
Section 3a
Interior finishing works have been completed by 80%.
Installation of the lift is in progress.
Installation of doors has begun.
Section 3b
Concreting of the floor slab of the 9th floor has been completed.
Concreting of vertical elements of the 10th floor has begun.
Laying of the internal walls of the 4th floor has begun.
Laying of the exterior walls of the 6th floor has been completed.
Glazing of the 4th floor has begun.
Section 3c
Installation of vertical elements of the 11th floor is completed.
Concreting of the floor slab of the 11th floor is completed.
Completion of the exterior walls of the 6th floor.
Laying of the internal walls of the 4th floor has begun.
Glazing of the 3rd floor is completed.
Section 3g
Concreting of the foundation slab is completed.
Section 3d
Installation of the basement floor slab is completed.
Concreting of vertical elements of the 1st floor is completed.
Concreting of the floor slab of the 1st floor is completed.
Concreting of vertical elements of the 2nd floor has begun.
Section 3e
Installation of vertical elements of the basement has begun.
Find out first about the company's news