Construction state of the residential area “Manhattan UP” as of 08.08.2023
Section A1
The roof is 90% complete.
Installation of elevators is 75% complete.
Internal electrical networks have been installed by 40%.
Section A2
Completed work on the masonry of the external roof parapet.
Facade works have been completed by 20%.
Internal drainage networks K1 and K2 are completed.
Internal water supply networks are completed.
Plastering of apartments with internal gypsum plaster on the 5th floor is 80% complete.
Installation of elevators has begun.
Section A3
Works on laying the internal walls of the 10th floor continue.
Laying of the exterior walls of the 11th floor has been completed.
Laying of the external walls of the 12th floor has begun.
Glazing of the 1st to 3rd floors has begun.
Section A4
Installation of formwork for the floor slab of the 6th floor is completed.
Reinforcement of the floor slab of the 6th floor has begun.
Laying of the exterior walls of the 3rd residential floor has begun.
Completed laying of the internal walls of the 2nd residential floor.
Section B1
Reinforcement of the foundation slab is completed.
Concreting of the foundation slab is completed.
Reinforcement of the vertical elements of the basement has begun.
Section B2
The excavation of the pit is 40% complete.