Construction state of the residential complex “A5” as of 02.16.2023
Construction state of the residential complex “A5” as of 02.16.2023
01/01
The exterior walls of the 5th floor are 60% complete.
Laying of the internal walls of the 4th floor is in progress.
Completed laying of the outer walls of the 4th floor.
Concreting of vertical elements is 90% complete.
The horizontal formwork of the floor slab on the 8th floor is in progress.