Completion of the exterior walls of the 5th floor.
Laying of the outer walls of the 6th floor has begun.
Laying of the internal walls of the 4th floor is in progress.
Concreting of vertical elements of the 9th floor is completed.
Reinforcement of the floor slab on the 9th floor is in progress.