Construction state of the residential complex A5 as of 05.05.2023
Sections 1-2
Completion of the exterior walls of the 7th floor.
The masonry of the internal walls of the 6th and 7th floors is 90% complete.
Concreting of vertical elements of the 11th floor is completed.
Concreting of the floor slab of the 11th floor is in progress.
Glazing of the 3rd floor is in progress.
Section 3
Concreting of the foundation slab is completed.
Reinforcement of vertical elements of the basement floor is in progress.