Construction state of the residential complex A5 as of 05.07.2023
Sections 1-2
Laying of the outer walls of the 10th and 11th floors has begun.
Laying of the internal walls of the 8th and 9th floors is in progress.
Installation of the floor slab of the 13th floor is completed.
Glazing of the 7th floor is completed.
Plastering of apartments on the 5th floor is in progress.
Facade installation has begun.
Section 3
Reinforcement of the floor slab of the 2nd floor is in progress.
Concreting of vertical elements of the 1st floor is completed.