Construction state of the residential complex A5 as of 07.08.2023
Sections 1-2
The masonry of the outer walls of the 10th and 11th floors has been completed.
The masonry of the internal walls of the 8th and 9th floors is 40% complete.
Glazing of the 10th floor is in progress.
Works on the facade are in progress.
Works on the commercial roof are in progress.
Section 3
Concreting of vertical elements of the 3rd floor is completed.
Formwork of the floor slab of the 3rd residential floor is in progress.