Construction state of the residential complex A5 as of 07.09.2023
Sections 1-2
The masonry of the internal walls of the 8th and 11th floors is 80% complete.
The glazing of the 10th floor has been completed.
The facade has been completed by 25%.
The roof of the commercial building is 80% complete.
Installation of the roof screed has begun.
Drilling and concreting of sheet pile piles is in progress.
Plastering works on the 7th floor of Section 2 are in progress.
Section 3
Concreting of vertical elements of the 5th floor is completed.
Concreting of the floor slab of the 5th floor is completed.
Works on reinforcement and concreting of walls and columns of the 6th residential floor are in progress.