0
We will call you back in 25 seconds
Order a call

Construction state of the residential complex A5 as of 07.11.2023

Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023
Construction state of the residential complex A5 as of 07.11.2023

01 /01

Sections 1-2 The masonry of the internal walls of the 9th and 10th floors has been completed by 50%. Commercial glazing is 60% complete. The facade is 65% complete. The roof of the commercial building is 90% complete. Works on plastering the walls of the 7th floor of the 2nd section have been completed. Plastering of the walls of the 11th floor is 50% complete. The excavation of the pit is completed. Arrangement of crushed stone preparation is completed. Reinforcement of the car park foundation slab is 80% complete. Installation of internal drainage networks K1 and K2 has begun. Section 3 Reinforcement of the floor slab of the 8th floor is completed. Concreting of the floor slab of the 8th floor has been completed. Installation of vertical elements of the 9th floor is completed. Installation of the floor slab of the 9th floor is completed. Installation of vertical elements of the 10th floor is completed. Installation of the floor slab of the 10th floor is completed. Installation of vertical elements of the 11th floor is completed. Completion of the external walls from the 3rd to the 6th residential floor. The masonry of the internal walls of the 1st residential floor is 80% complete. Laying of the internal walls of the 2nd residential floor is 80% complete. The masonry of the internal walls of the 3rd residential floor is 50% complete.
envelope

Find out first about the company's news