0
We will call you back in 25 seconds
Order a call

Construction state of the residential complex “IQ House” as of 04.05.2023

Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023

01 /01

Section 1 Laying of the external and internal walls of the 1st floor has begun. Section 2 Laying of the outer walls of the 5th floor has begun. Completed laying of the internal walls of the 4th and 5th floors. Section 3 The construction of vertical elements of the 6th floor is completed. The construction of the floor slab of the 6th floor is completed. Laying of the external walls of the 3rd floor is in progress. Installation of windows on the 1st floor has been completed.
envelope

Find out first about the company's news