Construction state of the residential complex “IQ House” as of 04.07.2023
Section 1
Completed laying of the outer walls of the 2nd floor.
Installation of the floor slab of the 4th floor is completed.
Installation of windows on the 1st floor is completed.
Pipe laying for domestic sewage, stormwater, water supply and cable products has been completed.
The crushed stone preparation of the basement slab has been completed.
Section 2
The masonry of the internal walls of the 6th floor is 80% complete.
Installation of vertical elements of the 8th floor has been completed.
Installation of the floor slab of the 8th floor has begun.
Pipe laying for domestic sewage, stormwater, water supply and cable products has been completed.
The crushed stone preparation of the basement slab has been completed.
Section 3
Laying of the outer walls of the 5th floor continues.
Installation of vertical elements of the 7th floor is completed.
Pipe laying for domestic sewage, stormwater, water supply and cable products has been completed.
The crushed stone preparation of the basement slab has been completed.