Construction state of the residential complex “IQ House” as of 06.12.2023
Section 1
Work on waterproofing the foundation has been completed.
The laying of the parapet has begun.
Installation of window structures is 70% complete.
Section 2
The roof has been completed.
Works on the facade have been completed by 60%.
Works on waterproofing of the foundation have been completed.
Plastering works in this section are completed.
Installation of the lift is 70% complete.
Installation of window structures is 70% complete.
Section 3
Plastering of the walls from the 5th to the 7th floor has been completed.
Works on waterproofing the foundation have been completed.
The masonry of the interior and inter-apartment walls of the 8th, 9th and 10th floors is in progress.
Installation of roof insulation has begun.
The facade has been completed by 30%.
Installation of window structures is 70% complete.