Construction state of the residential complex “IQ House” as of 11.04.2023
Section 1
The construction of vertical elements of the 3rd floor is completed.
Concreting of the floor slab of the 3rd floor has been completed.
Section 2
The construction of vertical elements of the 7th floor is completed.
Installation of the floor slab of the 7th floor is completed.
Laying of the exterior walls of the 4th floor has begun.
Completed laying of the internal walls of the 3rd floor.
Installation of windows on the 1st floor is completed.
Installation of windows on the 2nd and 3rd floors has begun.
Section 3
The construction of vertical elements of the 6th floor is completed.
Laying of the outer walls of the 2nd floor has begun.
The construction of the floor slab of the 6th floor has begun.