Construction state of the residential complex “MAIN HOUSE” as of 06.03.2023
Section 1
The facade works on the residential floors have been completed.
Entrances are 60% finished.
Installation of entrance doors to the apartments has been completed.
Works on the installation of heating networks are in progress.
Section 2
The roof has been completed.
Facade works are 40% complete.
Parking lot
The waterproofing of the 2nd bay of the parking lot has been completed.
Installation of the floor slab of the 4th bay of the parking lot has begun.
Landscaping
The paving is 40% complete.