Construction state of the residential complex “SKYGARDEN” as of 17.10.2023
Section 1
Concreting of the floor slab of the 0th floor has been completed.
Installation of vertical elements of the 1st floor is 14% complete.
Section 2
Formwork of the floor slab of the 0th floor is completed.
Installation of the floor slab of the 0th floor is completed.
Section 3
Works on crushed stone preparation for the foundation grillage have been completed.
Pile cutting works have been completed.
Installation of foundation grillage is 70% complete.
Installation of vertical elements of the 0th floor is 40% complete.
Section 4
Preparatory work is underway to arrange the crushed stone foundation for the monolithic grillage.
Construction of a transformer substation is in progress.
Installation of an auxiliary tower crane is in progress.
Section 5
Preparatory work has begun on the arrangement of crushed stone preparation for monolithic grillage.