Construction state of the residential complex “SKYGARDEN” as of 17.11.2023
Section 1
Concreting of vertical elements of the 2nd residential floor is completed.
Reinforcement of the floor slab of the 2nd residential floor is completed.
Concreting of the floor slab of the 2nd residential floor is completed.
Section 2
Reinforcement of vertical elements of the 2nd residential floor is completed.
Concreting of vertical elements of the 2nd residential floor completed
Installation of formwork for the floor slab of the 2nd residential floor has begun.
Section 3
Installation of formwork for the floor slab of the 1st residential floor has begun.
Section 4
Installation of foundation grillage has been completed.
Reinforcement of vertical elements of the 0th floor has begun.
Section 5
Pile cutting works have been completed.
Installation of foundation grillage has been completed.