Construction state of the residential complex “SKYGARDEN” as of 19.09.2023
Sections 1-2
Work continues on the installation of monolithic grillage.
Installation of the auxiliary tower crane has been completed.
Work has begun on the installation of vertical columns of the basement in section 1.
Section 3
Preparatory work on the installation of foundation grillage continues.
Preparations for the installation of a crane track for the auxiliary tower crane have begun.
Sections 4-5
The pile field in Section 4 has been completed.
The pit at section 5 has been completed.
Construction of a transformer substation is in progress.
Work has begun on the pile field.