Construction state of the residential complex “SKYGARDEN” as of 28.09.2023
Sections 1-2
The installation of foundation grillage is in progress (93% complete).
Work continues on the installation of vertical elements of the monolithic frame of the 0th floor.
The installation of monolithic grillage is 30% complete in Section 2.
Section 3
Work has begun on the installation of foundation grillage.
Preparations for the installation of a crane track for the auxiliary tower crane have been completed.
Preparatory work has begun on the installation of monolithic grillage.
Sections 4-5
Preparatory work has begun on the arrangement of crushed stone preparation for monolithic grillage.
The pile field in Section 5 is 37% complete.
Construction of a transformer substation is underway.
Installation of an auxiliary tower crane on sections 4 and 5 has begun.