Construction state of the residential complex “U ONE” as of 02.05.2023
Section 3
Installation of vertical elements of the 8th floor is completed.
Installation of the floor slab of the 8th floor is in progress.
Laying of the external walls of the 4th floor is completed.
Laying of the internal walls of the 3rd floor is in progress.
Glazing of the 2nd floor is completed.
Section 4
Installation of vertical elements of the 5th floor is completed.
Laying of the outer walls of the 2nd floor has begun.
Section 2
Installation of formwork for the floor slab of the 1st floor has begun.
Section 1
Works on pressing reinforced concrete piles have been completed.