Construction state of the residential complex “Union” as of 27.07.2023
Section A
Finishing of the hall is completed.
Section B
Finishing of the entrance is completed.
The hall is 90% finished.
Section C
The facade is 95% complete.
Finishing of the entrance is completed.
Finishing of the hall has begun.
Section D
Concreting of vertical elements of the 7th floor is completed.
Reinforcement of the floor slab of the 7th floor is in progress.
Laying of the external walls of the 4th floor is completed.
Laying of the internal walls of the 2nd floor is in progress.
Section E
Concreting of vertical elements of the 8th floor is underway.
Laying of the external walls of the 2nd floor is completed.
Laying of the internal walls of the 1st floor is in progress.
Commerce
Commercial glazing has begun.