Construction state of the U ONE residential complex as of 01.11.2023
Section 3
The glazing of the 12th floor has been completed.
Laying of the internal walls of the 10th and 11th floors is completed.
Laying of the internal walls of the 12th floor has begun.
Plastering of apartments from the 5th to the 9th floor is completed.
Plastering of apartments on the 10th floor is in progress.
The roof is 90% complete.
Facade works are underway.
Installation of air conditioning baskets has begun.
Section 4
The masonry of the outer walls of the 11th floor has been completed.
Glazing of the 6th, 7th and 8th floors has been completed.
Glazing of the 9th floor has begun.
Installation of a sloping semi-dry roof screed is completed.
Plastering of staircases is 80% complete.
Section 2
Installation of vertical elements of the 11th floor has been completed.
Installation of the floor slab of the 11th floor is completed.
Installation of vertical elements of the 12th floor completed.
Installation of formwork for the floor slab of the 12th floor has begun.
Section 1
Reinforcement of the floor slab of the 1st floor is completed.
Concreting of the floor slab of the 1st floor is completed.
Installation of vertical elements of the 2nd floor completed.
Installation of the floor slab on the 2nd floor is complete.
Work is underway on the installation of external water supply and sewage networks.