Construction state of the U ONE residential complex as of 02.03.2023
01 /01
Section 3
Installation of vertical elements of the 5th floor is completed.
Laying of the outer walls of the 2nd floor has begun.
Section 4
Installation of vertical elements of the 1st floor is completed.
Reinforcement of the 1st floor slab is completed.
Section 2
Installation of monolithic grillage and vertical elements of the 1st floor has begun.
Section 1
Works on pressing of reinforced concrete piles continue.