Construction state of the U ONE residential complex as of 11.07.2023
Section 3
Installation of the floor slab of the 13th floor is completed.
The masonry of the outer walls of the 10th floor has been completed.
Glazing of the 7th floor is in progress.
Section 4
Installation of vertical elements of the 10th floor is in progress.
Installation of the floor slab of the 9th floor is completed.
Section 2
Installation of vertical elements of the 6th floor continues.
Installation of the floor slab of the 5th floor is completed.
Section 1
Installation of monolithic grillage is 90% complete.
Installation of vertical elements of the 1st floor is 60% complete.