Construction state of the U ONE residential complex as of 11.10.2023
Section 3
Glazing of the 11th floor is completed.
Glazing of the 12th floor is 80% complete.
Completed laying of the internal walls of the 9th floor.
Laying of the internal walls of the 10th floor has begun.
Plastering of apartments on the 5th and 6th floors is in progress.
The roof is 70% complete.
Facade works have begun.
Section 4
Completed laying of the outer walls of the 10th floor.
Laying of the outer walls of the 11th floor has begun.
Glazing of the 5th floor is completed.
Glazing of the 6th floor has begun.
Installation of a sloping semi-dry screed has begun.
Plastering of staircases is in progress.
Section 2
Installation of the 9th floor slab is completed.
Installation of vertical elements of the 10th floor is complete.
Installation of the floor slab of the 10th floor is completed.
Installation of vertical elements of the 11th floor has begun.
Section 1
Installation of vertical elements of the 1st floor completed.
Reinforcement of the floor slab on the 1st floor has begun.
Works on the installation of external water supply and sewage networks are in progress.