0
We will call you back in 25 seconds
Order a call

Construction state of the U ONE residential complex as of 14.11.2023

Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023
Construction state of the U ONE residential complex as of 14.11.2023

01 /01

Section 3 Laying of the internal walls of the 12th floor is in progress. Plastering of apartments on the 10th and 11th floors has been completed. Plastering of apartments on the 12th floor has begun. Roofing is 95% complete. Facade works are 20% complete. Installation of air conditioning baskets is in progress. Section 4 The masonry of the outer walls of the 12th floor has been completed. The masonry of the technical floor has been completed. Glazing of the 9th floor is completed. Glazing of the 10th floor is in progress. Plastering of staircases is 85% complete. Section 2 Installation of the formwork for the floor slab of the 12th floor has been completed. Installation of the floor slab of the 12th floor is completed. Reinforcement of the vertical elements of the 12th floor has been completed. Section 1 Installation of vertical elements of the 3rd floor completed. Reinforcement of the floor slab of the 3rd floor is completed. Works on the installation of external water supply and sewage networks are underway.
envelope

Find out first about the company's news